An investor building a plant chooses not only a contractor but also a contract model. The two most common are EPC and EPCM.
EPC: single-point responsibility
Under an EPC contract the contractor designs the facility, procures equipment and materials, builds and hands it over turnkey — usually for a fixed price and on a fixed schedule.
- Pros: clear budget, one point of responsibility, minimal management load on the client.
- Cons: the contractor prices in risk; the client has less influence over supplier selection.
EPCM: management on the client’s behalf
Under an EPCM contract the contractor designs and manages procurement and construction, but the client signs the supply and construction contracts directly.
- Pros: cost transparency, flexibility, client control over procurement.
- Cons: overrun risk stays with the client; a strong owner’s team is needed.
| Criterion | EPC | EPCM |
|---|---|---|
| Cost risk | contractor | client |
| Procurement control | contractor | client |
| Load on owner’s team | low | medium |
| Best for | proven technologies, project finance | unique technologies, in-house procurement expertise |